Conditions for conversion

70. As a condition for conversion of a chemical weapons production facility for purposes not prohibited under this Convention; all specialized equipment at the facility must be destroyed and all special features of buildings and structures that distinguish them from buildings and structures normally used for purposes not prohibited under this Convention and not involving Schedule 1 chemicals must be eliminated.

71.  A converted facility shall not be used:

         (a) For any activity involving production, processing, or consumption of a Schedule 1 chemical or a Schedule 2 chemical; or

         (b) For the production of any highly toxic chemical, including any highly toxic organophosphorus chemical, or for any other activity that would require special equipment for handling highly toxic or highly corrosive chemicals, unless the Executive Council decides that such production or activity would pose no risk to the object and purpose of this Convention, taking into account criteria for toxicity, corrosiveness and, if applicable, other technical factors, to be considered and approved by the Conference pursuant to Article VIII, paragraph 21 (i).

72.  Conversion of a chemical weapons production facility shall be completed not later than six years after entry into force of this Convention.

Decisions by the Executive Council and the Conference

73.  Not later than 90 days after receipt of the request by the Director-General, an initial inspection of the facility shall be conducted by the Technical Secretariat. The purpose of this inspection shall be to determine the accuracy of the information provided in the request, to obtain information on the technical characteristics of the proposed converted facility, and to assess the conditions under which use for purposes not prohibited under this Convention may be permitted. The Director-General shall promptly submit a report to the Executive Council; the Conference, and all States Parties containing his recommendations on the measures necessary to convert the facility to purposes not prohibited under this Convention and to provide assurance that the converted facility will be used only for purposes not prohibited under this Convention.

74.  If the facility has been used for purposes not prohibited under this Convention before this Convention enters into force for the State Party, and is continuing to be in operation, but the measures required to be certified under paragraph 68 have not been taken, the Director-General shall immediately inform the Executive Council, which